Kochi: Even after allocating huge amount for construction of 199 apartment units with 300 sq ft each for rehabilitation of people living in colonies Mattancherry below Rajiv Awas Yojana (RAY) Scheme, Kochi Corporation Unable to complete work on the project. Corporation officials, who have extended the deadline four times earlier, are planning to extend it once again.
As per the original schedule, the work should have been completed by 2018. Now, officials are seeking the council’s approval to extend the deadline for the fifth time.
In addition, the corporation officials have kept files related to works other than civil works, amounting to about Rs 6 crore. During the tenure of the previous council, the corporation officials had inflated the estimate of the project by more than 100%.
During 2019-20, the auditors found serious discrepancies in the revision of estimates of the ground plus 11-storey apartment complex. According to the audit report for 2019-20, which is out now, around 975 housing units for the poor could have been constructed using Rs 39 crore, which is what the local body has for building just 199 units of 300 sq ft. Prepared estimate.
In 2016, the corporation officials prepared an estimate of Rs 14 crore for the construction of the apartment complex, where 199 housing units of 300 sq ft are to be constructed in Mattancherry under the RAY project. The corporation awarded the work to a contractor in 2017 at a revised rate of Rs 18 crore.
The contractor could complete the work of one and a half floor even after two years. Then, the corporation revised the estimate to Rs 39 crore without sufficient reasons. Opposition leader Antony Kurithara said, “It is a grave injustice to keep poor homeless people waiting desperately.”
as well as mayor M Anil Kumar Said that the corporation is taking all measures to complete the work.
“When we took over two years ago, civil work was completed on only one floor. Now, civil work has been completed on nine of the total 12 floors,” he said.