Audit to check structural flaws in 15 highrise societies in second phase, ET Real Estate

[ad_1]

Gurugram: Deputy commissioner Nishant Yadav Structural audit of 15 housing societies in the city was ordered on Friday, kicking off the second phase of an exercise carried out after vertical collapse of flats. Chintel Paradiso Last year. The societies will be selected from among 60 projects whose residents and RWAs complained about the quality of construction and structural defects in the last two years.

most of them are with Dwarka Expressway and the Southern Peripheral Road, which includes roads built by major real estate firms.

“Keeping in view the seriousness of the matter and the larger public interest, the District Town Planner has been asked to conduct a preliminary visual survey of all the 60 societies to select 15 most important ones where structural audit should be carried out on priority.” Said. The process will include on-site inspection of buildings to check for any obvious defects, and signs of wear and damage to slabs, columns and beams.

The first phase of the audit – which also covers 15 societies – was ordered in August 2022, months after a sixth-floor flat caved in, triggering a vertical collapse of floors to the first floor of a tower. Chintel Paradiso In Sector 109 on 10 February. Two women died in the cave, which was later attributed to structural deficiencies of the building. Four agencies drawn up by the district administration – Bureau Vertias, TPC Technical Projects Consultants, Wintech Consultants and NNC Design International – conducted the audits in September and later submitted reports pointing out several deficiencies. Prominent among them were leaks and flooding in basements, corrosion of steel and peeling of plaster. But the issues were “repairable,” the agencies concluded. The first phase included societies such as Mapsco Casabella Sector 82, Park Place in DLF-5, Paras Irene in Sector 70A, among others.

After selecting another batch of 15 societies, DTP Manish Yadav will write to RWAs, asking them to get audited by agencies empaneled by the district administration or a consultant of their choice.

The cost of the audit will be borne equally by the RWA/residents and the developer. The Deputy Commissioner said that if the complaint of lack of RWAs is found to be true, the developer will have to pay the full cost.

The audit process will be the same as in the first phase.

The administration also wants to involve officials from the Planning Department and PWD as the enforcement wing of the Town and Country Planning Department (DTCP) is short of staff. Officials said this would ensure that the exercise is completed in a stipulated time frame.

  • Published on May 27, 2023 at 09:21 am IST

Join a community of 2M+ industry professionals

Subscribe to our newsletter to receive the latest insights and analysis.

Download e-Realty App

  • get realtime updates
  • Save your favorite articles


scan to download app


[ad_2]

Source link

Leave a Reply

Your email address will not be published. Required fields are marked *